How To Build a 100 cu. ft./day Methane Gas Plant
(These instructions are for an underground,
single-.stage, double-chamber plant designed to digest 100
pounds of manure every 24 hours — five cows'
worth — but may be scaled upward to
construct a plant capable of producing 500 feet of gas a
day).
Dig a hole 13 feet deep and 12 feet in diameter, cutting
away trenches for the inlet and outlet pipes to angle down
through.
In the center of the hole, pour a slab of concrete six
inches thick and six feet in diameter. The composition of
the concrete should be 1 part cement, 4 parts sand and 8
parts of 1" stone aggregate.
The digester will be built on this base from 1:2:4 concrete
using 1/2" aggregate. The floor and walls will be 3" thick,
giving an inside diameter of 5'6". The walls will be 16'
high and reinforced with eight 3/8" machine steel vertical
rods and 15 horizontal rings of the same material.
Inlet and outlet pipes of 4" galvanized iron should be
positioned before pouring the walls so that the pipes are
positioned 1-1/2' above the digester floor and in from the
walls. This is so that when the dividing wall is built
across the center of the digester, each pipe will be
centered in its chamber. The concrete must be tightly
packed around the pipes to prevent leakage.
Another wall of brick or concrete will be built three feet
outside the digester wall and to the same height (i.e. four
feet above ground level). This space will be filled with an
insulating material: straw, sawdust, shavings, etc.
Provide some means of descending into this space —
perhaps rungs of machine steel rod extending from the
digester wall to the brick retaining wall — in case
it should ever become necessary to empty the insulation.
Seal the top of this area to prevent water from getting in,
and leave bare earth in the bottom for drainage.
Bisecting the digester will be a wall of 4" reinforced
concrete eight feet high, at the top of which an iron
support structure with a guide pipe for the gas collector
will be placed. This structure is made of angle iron and
the guide pipe is eight feet of 3" galvanized iron pipe.
The structure will be set in the digester walls and solidly
fixed atop the chamber-dividing wall. The pipe must be in
the exact center of the digester, allowing the gas
collector to descend into the slurry when empty and rise to
ground level when full. This requires 4' of vertical
travel, thus the top eight feet of the digester are left
for the gas collector while the bottom eight feet contain
the dividing wall.
The gas collector is a roofed cylinder five feet in
diameter and four feet high constructed of 12-gauge machine
steel sheeting. It is braced internally with angle irons
fitted at different heights so that when the collector is
rotated around its guide pipe the scum on the surface of
the slurry will be broken. The cylinder will first be
riveted, welded, tested for leaks by filling with water and
finish-welded. After all leaks are sealed it should be
given two coats of enamel paint inside and out. The top
will be covered with an insulating material.
The top of the gas collector is also fitted with a 1" tap
and valve, and to this is connected a flexible pipe leading
to your gas appliances. Inside the tap a piece of wire mesh
is attached to serve as a flame arrester. The actual
capacity of the gas holder is less than 100 cubic feet, but
if the gas is being used regularly there's no need to make
it larger.
The mixing tank is a cylinder 2'4" in diameter and two feet
high. Its floor is one foot above ground level to provide
hydraulic head to feed the plant. The inlet pipe opening is
flush with the bottom of the mixing tank and is covered
with a coarse screen to prevent large pieces of waste from
being ingested. The tank may be built of bricks or concrete
and is about 8-1/2 cubic feet in volume, sufficient for the
daily charge of waste matter.
The discharge pit should be large enough to accommodate all
the spent slurry that is expected to accumulate at a time.
It's made of bricks or concrete and the discharge end of
the outlet pipe should be just even with ground level.
An earth walkway at least three feet wide and level with
the top of the plant should be raised outside the brick
wall for support and additional insulation.
Approximate cost of materials for this plant in the United
States is $400.