THE RETURN OF THE CORDWOOD HOUSE
(Page 7 of 11)
September/October 1977
By the Mother Earth News editors
WALL CONSTRUCTION
RELATED CONTENT
You don't have to buy or rent a lot of expensive equipment to handle your tough homestead lifting j...
Jack Park's Wind Experiments March/April 1975 Some of the more interesting wind power experiments(b...
After 1,500 miles of alternative fuels vehicle driving, we found that you can run a truck with a wo...
Almost half the world’s original forests have disappeared, one-fifth since the late 1950s....
Prior to the actual laying of logs to form walls, the foundationcomprised of a network of railway ties-was accurately placed surrounding the previously positioned water tank. The railway ties network was 36 X 16 feet and was made up of a pair of ties running parallel 24" apart (outside measurement) and interconnecting at the corners. The foundation was squared by a right-angle triangle method and covered by polyethylene. Second, the building materials and equipment needed in wall construction were transported to the site. Included were 200 cubic feet of wood shavings and the first of many loads of hand-shovelled sand from a nearby pit. Also obtained, in anticipation of colder weather conditions, was a 1,000-board-foot bundle of 2 X 4's to be used in the construction of a polyethylene enclosure-40 feet long, 28 feet wide, and 10 feet high-in order to cover the building and provide a small working area. The enclosure was initially heated by a small 100,000 Btu/hr. propane heater during the night; however, as average temperatures dropped, a larger 350,000 Btu/hr. heater and accessory generator were required almost continuously.
The initial wall construction was done by a crew of six. One mixed mortar (ratio . . . 5 sand : 2 cement : 1 lime) in a gasoline powered mixer; another hauled the mortar by wheelbarrow to the various locations. In addition, he supplied the builders with sufficient logs, 8 X 8 blocks, and shavings so work could continue uninterrupted. Two worked on corners, which involved laying the mortar on the foundation and placing two 30" 8 X 8 sawn-three-sides blocks 24" apart (outside measurement). Then more mortar was applied between the blocks' exposed faces and a log inserted along with shavings to fill the inner gap. (The shavings were mixed with hydrated lime to prevent insect infestation . . approximately one shovelful of lime per wheelbarrow of shavings.) Next, mortar beads were placed along the edges of the already positioned blocks and two more blocks were placed perpendicularly to them. Then a log and shavings were again placed in the gap and the process continued.
Once the corners were built up, log layering could proceed. This entailed laying a bead of mortar along the foundation, approximately 3" on the inside and outside edges of the ties, then filling the gap with shavings. A log was then placed in position and another bead of mortar applied on that log's inside and outside edges. Shavings were packed in that gap and another log positioned. This was done, of course, in rows along the entire length of the wall, using larger diameter wood at the base of the wall.
The fact that the corner construction was allowed to proceed ahead of log-laying enabled the two men laying logs to use a string line, which kept the wall section plumb and straight, with the corners as end points. The corners were set level and plumb as each layer was added, and the mortar was allowed to set before the corners were used as reference end points. Upon setting, the mortar was finished with a masonry jointer to a depth of 1/4" into the surface of the wall, thus accenting the log composition of the wall.
Page:
<< Previous 1 |
2 |
3 |
4 |
5 |
6 | 7 |
8 |
9 |
10 |
11 |
Next >>