PERMITS AND FEES
RELATED CONTENT
'How to Become Food Self-Sufficient' Competition
November/December 1974
By the Mother ...
A SELF-SUFFICIENT ENERGY/LIVESTOCK SYSTEM November/December 1980 An innovative Missourian shows us ...
With motivation, hard word and an internet connection, the dream of going back to the land is more ...
A Plowboy Interview with Steve Brown and Victor Schiff founders of the Ecological Food Society....
GARY SKEEM: AN INDEPENDENT IDAHOAN November/December 1979 Issue # 60 - November/December 1979 In so...
Before you can build or renovate a structure, you must submit your plans to the local Building Inspector for approval and pay the applicable permit fees. If the building is a standard-construction "conventionally framed dwelling" of stud wall or masonry construction, you can submit your own plans. The inspector will examine the plans for compliance with the codes. If they are suitable, they will be approved. Then you pay a permit fee based on the number of square feet in the building. There is a standard fee list for each area that you can see before paying a fee. At the time plans are approved, one-half of the stated building fee must be paid.
Other permits must be obtained for plumbing and electrical facilities and additional fees paid. These fees are based on the number of outlets to be built into the dwelling.
INSPECTIONS AND CERTIFICATION OF OCCUPATION
Once your plans are approved and a permit is issued you can build the house yourself. The law does not require you to hire professional builders. During construction many building departments make four inspections. The first is to look at the foundation before it is laid. The second is a frame inspection after the roof framing and basing are in place and pipes, chimneys, and vents are complete. The third is the wall inspection before plastering or siding is commenced. The fourth, and final, inspection comes after the building is completed and ready for occupancy. Many rural areas only require a single inspection after the house is completed.
Before a home can be lived in and after the final inspection, the building department will often be required to issue a Certificate of Occupancy. If you are buying a newly constructed house, be sure it has been certified properly.
GETTING AN UNCONVENTIONAL STRUCTURE APPROVED
If you intend to build an unusually designed dwelling, you will be required to write to the International Conference of Building Officials (see USEFUL RESOURCES at the end of this chapter) to see if they have any approved plans for such a structure. They have approved standard plans for common unconventional designs, such as domes and round houses. In most areas, to get approval of an unconventional design, you must have specific plans drawn up by a licensed engineer or contractor.
TEST FOR STRUCTURAL STRENGTH
The Uniform Building Code provides that if a structure does not meet normal code requirements, the local Building Inspector may conduct a test for structural strength on the building before it can be approved. In many cases, you will have to hire a structural engineer to conduct these tests to the satisfaction of the building department. Because of the growing popularity of domes, some companies have conducted strength tests on plywood domes. If you plan a dome, write for the results of tests undertaken by :